October 20, 2014
Nathan Newell

Drywall mud and tape

October 20, 2014
Nathan Newell

Our plumbing, electric, and HVAC is completed. M&M Drywall is taping and starting the hand-trowel texture. Paint on Monday on the interior and the trim will come soon after. The fireplace will be rocked first week of November. Our first guests arrive on December 5. This is so exciting!!

Looking down on the Great Room

image.jpg

An upstairs bedroom

October 20, 2014
Nathan Newell

Nathan Newell

View from North Road
2nd Floor
 